top of page

FEATURED PROJECTS

Project: Plans & Permits

Moose Creek Tank Farm Facility

 

A large 500,000-barrel bulk fuel storage facility was constructed near North Pole, Alaska, between 2020 and 2021. Integrity Environmental LLC was chosen to perform all the environmental operational permitting at the local, state, and federal levels.  

The site was particularly challenging due to the developing state and federal regulations surrounding perfluorooctanoic acid and perfluorooctane sulfonate (referred to as PFOA and PFOS, respectively). These are fluorinated organic compounds that are part of a larger group of compounds known collectively as perfluoroalkyl substances (PFAS). The groundwater underlying the site had been historically contaminated with PFAS by the nearby Air Force base.  

 

By the time the operational planning process started, the State of Alaska had drastically changed how it allowed PFAS-contaminated water to be used. The State also declared a Critical Water Management area in the exact location of the tank farm project. This presented critical engineering challenges.

Integrity Consultants worked with State regulators within the Alaska Division of Mining, Land and Water and the Alaska Department of Environmental Conservation to determine how the developing PFAS guidelines would impact the engineering of the fire-fighting system and the tank construction. Impacts on stormwater management and oil spill response tactics used at the site were also analyzed and adapted to minimize interaction with the contaminated water.  

In a typical tank farm construction project, large amounts of water are used in tank integrity testing and firefighting systems. However, there was no other viable water source at the North Pole site because the groundwater was contaminated with PFAS. Alternative testing methods allowed under the engineering standard API 650 had to be utilized, and an alternative firefighting system had to be developed.  

Integrity’s permitting experts played a vital role in finding solutions and working with the State of Alaska to approve alternative API 650 testing methods, design changes, and an effective Oil Discharge Prevention and Contingency Plan (ODPCP). Our consultants’ vast knowledge of State regulations and the API 650 standard strongly supported the project.  

Despite its unique challenges, this tank farm was finished and ready for operations at the beginning of 2022. Integrity was lauded by the Project Team for their professionalism, ability to meet permit issuance timelines despite the many unanticipated changes, and attention to detail on all State submittals and record keeping.  

Project 1
Project 2

Project: Inspection

On-going Contracted Inspection Program

Since 2017, Integrity has managed a cost-effective and efficient annual tank inspection program for a company with multiple facility locations across South East and South Central Alaska. This program manages the inspections for hundreds of field-constructed and shop-built tanks.

 

Integrity provides historic inspection auditing, develops an annual inspection plan, and performs all API 653 internal and external inspections, STI SP001 inspections, API 570 piping inspections, and annual cathodic protection system surveys. Because our lead inspector is on-site for all inspections, Integrity also performs NDE services on areas of concern, identifies potential problems early, and partners with local contractors to provide tank, pipeline, and containment repairs.

 

This program has resulted in the elimination of late or missed inspections, saved the client money by planning ahead for cost savings, and strengthened the client’s relationships with the State of Alaska and federal regulatory agencies as well written and easy-to-read reports are delivered on-time year after year.

Project 3

Project: Consulting

Rural Bulk Fuel Facility Upgrade

Integrity was contracted in by the joint owners of a highly remote rural facility in 2018 to assess the condition of the infrastructure and to assess regulatory compliance with applicable plans and permits in place. Integrity’s final analysis report guided a targeted $475,000 engineering improvement project that repaired four of the six horizontal fuel storage tanks to STI SP001 standards, replacement of all water draw nozzles, piping, and pumps, replacement of the dispensing mechanism, and added considerations for safety, building, and fire codes.  Integrity partnered with the design engineering and mechanical repair teams and gave significant input into the design and repair options. All permits and plans were updated to streamline record-keeping and reporting requirements. All on-site personnel received quality training in record-keeping, annual maintenance requirements, and general housekeeping and inspection checklists. 

Integrity’s strong communication skills and network with local, state, and federal regulators ensured compliance at this facility with no loss of integrity, no notices of violation, and in partnership with the local community. This project extended the facility life to over 20 years, improved safety for facility personnel and community members utilizing the card lock station, significantly reduced risk exposure for the owners, and increased fuel storage capacity for the community.

Of note in this project was the cost savings for rehabilitating and repairing tanks rather than replacing them and using a phased repair schedule to ensure ullage was available around the limited barge delivery schedule available in this remote location. It is estimated that this approach saved the clients $725,000 by avoiding a complete facility replacement.

bottom of page